SECTION: 23 64 26 CHILLED, CHILLED-HOT, & CONDENSER WATER PIPING
Criteria
- UFGS 23 64 26 CHILLED, CHILLED-HOT, & CONDENSER WATER PIPING
- Resource Conservation and Recovery Act (RCRA) , Section 6002
- Federal Sustainable Acquisition Items/Requirements
- DoD Green Procurement Policy (Aug 27 2004)
- DoD Green Procurement Strategy (Nov 2008)
- Army Green Procurement Policy (Nov 22 2006)
- Federal Acquisition Regulation, Part 23
- EPA Final Guidance on Environmentally Preferable Purchasing
- HJB Form 225 (JBLM Sustainable Acquisition Exception Form)
- UFC 1-200-2 (High Performance and Sustainable Buildings Requirements)
- ASA IE&E Sustainable Design and Development Policy (Jan 17 2017)
Changes or Criteria Notes to Unified Facilities Guide Specifications (UFGS)
Paragraph # and Title (if any) |
Note to Designer |
Change Text |
1.3 SUBMITTALS |
If 01 33 29 is not incorporated in the specifications, change reference to 01 33 29 in this section to instead say 01 57 19.01 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS and ensure the additional sustainable acquisition language at paragraphs "Submittals" and "Sustainable Acquisition" of 01 57 19.01 20 is included within that section. |
|
1.3 SUBMITTALS |
As applicable based on project scope, add the following under "SD-01 Preconstruction Submittals" and "SD-11 Closeout Submittals": |
Insulation (Recycled Content); S |
2.15 FACTORY APPLIED INSULATION |
[NOTE: In the column to the right, select 01 33 29 when it is incorporated into the specifications, otherwise select 01 57 19.01 20 and ensure it includes added sustainable acquisition language at paragraphs "Submittals" and "Sustainable Acquisition" of that section]
Revise content as follows:
|
Provide products and documentation meeting the requirements at Section [01 33 29 SUSTAINABILITY REPORTING][01 57 19.01 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS] paragraph RECYCLED CONTENT. See https://sftool.gov/greenprocurement/green-products/1/construction-materia./building-insulation/0?addon=False and https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program for more information. |
2.17.3 FIELD APPLIED INSULATINO |
[NOTE: In the column to the right, select 01 33 29 when it is incorporated into the specifications, otherwise select 01 57 19.01 20 and ensure it includes added sustainable acquisition language at paragraphs "Submittals" and "Sustainable Acquisition" of that section]
Revise content as follows:
|
Provide products and documentation meeting the requirements at Section [01 33 29 SUSTAINABILITY REPORTING][01 57 19.01 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS] paragraph RECYCLED CONTENT. See https://sftool.gov/greenprocurement/green-products/1/construction-materia./building-insulation/0?addon=False and https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program for more information. |
Design Requirements
Where piping is subject to the potential for freezing it shall be provided with a 30% glycol mixture as a freeze prevention measure.
Notes to Designers on Drawing Content
Standard Details
Applicable Points of Contact
Design Standards