SECTION: 02 83 13.00 20 LEAD IN CONSTRUCTION
Criteria
- Quality Assurance: EP 415-1-261, Volume 1
- UFGS SECTION 02 83 13.00 20 LEAD IN CONSTRUCTION. Use this section for lead based paint (LBP) abatement tasks on Joint Base Lewis-McChord (JBLM), when design is being performed for JBLMs Public Works Engineering Services Division and/or Corps of Engineers contract vehicles for solicitation and award, for other than "Target Facilities" (facilities where occupants could include minors less than 6 years of age, i.e. housing or child care facilities). This section 02 83 13.00 20 will be used for such general construction work in which lead based paint will be disturbed. Section 02 83 19.00 10 will be used for LBP work in Target Facilities and Child Occupied Facilities.
Changes or Criteria Notes to Unified Facilities Guide Specifications (UFGS)
Paragraph # and Title (if any) | Note to Designer | Change Text |
1.1 References | Delete the following references: | Delete "16 VAC 25-35" and "08 VAC 15-30" |
Design Requirements
Joint Base Lewis-McChord is committed to protect and conserve the environment. All maintenance, repair and construction work on the installation will comply with all applicable environmental policy, laws and regulations; identify potential sources of pollution and meet or exceed Army goals for prevention of pollution and minimize adverse environmental impacts.
Notes to Designers on Drawing Content
Provide LBP abatement plans as required to show locations of samples taken/location of hazardous materials. These may be attached to appropriate specification section with survey data or incorporated into the Contract drawings if complexity warrants.
Standard Details
Applicable Points of Contact
Design Standards