SECTION: 02 83 00 LEAD REMEDIATION
 

Criteria

  1. Quality Assurance: EP 415-1-261, Volume 1
  2. UFGS SECTION 02 83 00
 

Changes or Criteria Notes to Unified Facilities Guide Specifications (UFGS)

 

SECTION 02 83 00  LEAD REMEDIATION

 

Design Requirements

Joint Base Lewis-McChord is committed to protect and conserve the environment. All maintenance, repair and construction work on the installation will comply with all applicable environmental policy, laws and regulations; identify potential sources of pollution and meet or exceed Army goals for prevention of pollution and minimize adverse environmental impacts.

 

 

Notes to Designers on Drawing Content

Provide LBP abatement plans as required to show locations of samples taken/location of hazardous materials. These may be attached to appropriate specification section with survey data or incorporated into the Contract drawings if complexity warrants.

 

 

Standard Details

 

 

Applicable Points of Contact

Design Standards