SECTION: 02 82 00 ASBESTOS REMEDIATION
 

Criteria

  1. Quality Assurance: EP 415-1-261, Volume 1
  2. UFGS  SECTION 02 82 00 ASBESTOS REMEDIATION
  3. EP 1110-1-11 Engineering and Design - Asbestos Abatement Guideline Detail Sheets - SPECIFY THE USE ONLY OF DETAIL SHEET 19, titled: "Certification of Final Cleaning and Visual Inspection" found on page 51; unless particular project requires specific prescriptive approaches.
  4. Farm Security and Rural Investment Act of 2002, Section 9002
  5. Federal Sustainable Acquisition Items/Requirements
  6. DoD Green Procurement Policy (Aug 27 2004)
  7. DoD Green Procurement Strategy (Nov 2008)
  8. Army Green Procurement Policy (Nov 22 2006)
  9. Federal Acquisition Regulation, Part 23
  10. USDA BioPreferred Program
  11. EPA Final Guidance on Environmentally Preferable Purchasing
  12. HJB Form 225 (JBLM Sustainable Acquisition Exception Form)
  13. UFC 1-200-2 (High Performance and Sustainable Buildings Requirements)
  14. ASA IE&E Sustainable Design and Development Policy (Jan 17 2017)

 

Changes or Criteria Notes to Unified Facilities Guide Specifications (UFGS)

 

02 82 00 ASBESTOS REMEDIATION

 

VISUAL CLEARANCE BLANK FORM

 

Design Requirements

Joint Base Lewis-McChord is committed to protect and conserve the environment. All maintenance, repair and construction work on the installation will comply with all applicable environmental policy, laws and regulations; identify potential sources of pollution and meet or exceed Army goals for prevention of pollution and minimize adverse environmental impacts.

 

 

Notes to Designers on Drawing Content

Provide ACM abatement plans as required to show locations of samples taken/location of hazardous materials. These may be attached to appropriate specification section with survey data or incorporated into the Contract drawings if complexity warrants.

 

 

Standard Details

Refer to Criteria Section, above

 

 

Applicable Points of Contact

Design Standards